Reference project track-foundation-laying train: Foundation for a signal bracket in Hamburg

A pile was driven in as the foundation for a signal bracket during the construction of the new S4 S-Bahn (suburban) railway link (Hamburg – Bad Oldesloe). The foundation was located on an embankment between the tracks of the S1 S-Bahn rail link and the mainline railway – it was therefore not possible to access it from the outside – but that was a situation for which the track-foundation-laying train was literally designed for.

The track-foundation-laying train allowed the workers to complete the foundation for a signal bracket in an inaccessible location within less than 40 hours – and without the need to dismantle any railway infrastructure. A total success!

Vorschaubild YouTube Video

Foundation in just 40 hours - the work flow:

2.00 a.m.: The shoring work began at the foundation point once the construction track had been installed. The track-foundation-laying train was prepared at a nearby suburban railway siding at the same time. The foundation pipe (DN 813) was attached to the hydraulic vibrator and vibrated 6.5 metres into the ground along with the welded-on side plates once the track-foundation-laying train had been positioned at the foundation point. The track-foundation-laying train was then converted on site to the Kelly drilling method for the purposes of boring out the foundation pipe down to the base.

The foundation pile was concreted with the reinforcement cage having been lifted into place that same evening.

The reinforcement work for the head foundation with the integrated anchor rods as a connection for the signal bracket to be fitted later was commenced the next morning.

The prefabricated concrete element was placed over the lost formwork, the anchor rods were aligned for the final time and the head foundation was concreted at around midday.

Construction panel

Client:

Depenbrock Bau GmbH & Co. KG, 32351 Stemwede

Construction time:

Around 40 hours, 18./19.11.2023

Scope of work:

Installation of the foundation for a signal bracket with head foundation

HERING reference projects Foundation Construction Train:

Heavy duty machinery and Foundation Construction Train: News

Heavy Lifting, Strong Teamwork: Construction Site Hamburg–Krabbenkamp

A strong performance through the perfect coordination of HERING Rail Construction, our heavy machinery fleet, and the rail logistics team of HERING Railway Services.

BR218 Locomotive with RES Wagons

In Hamburg-Billwerder, a 36-metre-long torsion beam weighing 40 tonnes and two concrete columns, each 15 metres long (weighing 16 and 10 tonnes respectively), were loaded onto a total of five RES wagons using a mobile crane. The components were then transported approximately 15 kilometres to the Krabbenkamp construction site by our BR218 locomotive “Hartmut”.

Once on site, the components were installed with millimetre precision in a tandem lift operation using our cranes KRC 810/3 and KRC 810/4 “Popeye”.

Teamwork, precision, and powerful technology – that’s how we deliver major projects safely and successfully!

Tandem Lift Operation with Cranes KRC 810/3 and KRC 810/4
EMAS-Logo

HERING sustainability

At HERING, we see ourselves as pioneers in the field of sustainability. As early as 1996, we were the first construction company in Germany to obtain EMAS certification. Every three years, we publish an environmental statement documenting our goals and how we have achieved them. Actually, for the first time, we published a sustainability report with an integrated environmental statement in accordance with EMAS - a logical next step in view of our ecological and social responsibility. It documents how we deal internally and externally with the issues that are essential to our future viability.

Exhibitions / Events

Heavy Lifting, Strong Teamwork: Construction Site Hamburg–Krabbenkamp

A strong performance through the perfect coordination of HERING Rail Construction, our heavy machinery fleet, and the rail logistics team of HERING Railway Services.

BR218 Locomotive with RES Wagons

In Hamburg-Billwerder, a 36-metre-long torsion beam weighing 40 tonnes and two concrete columns, each 15 metres long (weighing 16 and 10 tonnes respectively), were loaded onto a total of five RES wagons using a mobile crane. The components were then transported approximately 15 kilometres to the Krabbenkamp construction site by our BR218 locomotive “Hartmut”.

Once on site, the components were installed with millimetre precision in a tandem lift operation using our cranes KRC 810/3 and KRC 810/4 “Popeye”.

Teamwork, precision, and powerful technology – that’s how we deliver major projects safely and successfully!

Tandem Lift Operation with Cranes KRC 810/3 and KRC 810/4