Foundation Construction Train
Track Foundations with HERING

Reference project track-foundation-laying train: Foundation for a signal bracket in Hamburg

A pile was driven in as the foundation for a signal bracket during the construction of the new S4 S-Bahn (suburban) railway link (Hamburg – Bad Oldesloe). The foundation was located on an embankment between the tracks of the S1 S-Bahn rail link and the mainline railway – it was therefore not possible to access it from the outside – but that was a situation for which the track-foundation-laying train was literally designed for.

The track-foundation-laying train allowed the workers to complete the foundation for a signal bracket in an inaccessible location within less than 40 hours – and without the need to dismantle any railway infrastructure. A total success!

Vorschaubild YouTube Video

Foundation in just 40 hours - the work flow:

2.00 a.m.: The shoring work began at the foundation point once the construction track had been installed. The track-foundation-laying train was prepared at a nearby suburban railway siding at the same time. The foundation pipe (DN 813) was attached to the hydraulic vibrator and vibrated 6.5 metres into the ground along with the welded-on side plates once the track-foundation-laying train had been positioned at the foundation point. The track-foundation-laying train was then converted on site to the Kelly drilling method for the purposes of boring out the foundation pipe down to the base.

The foundation pile was concreted with the reinforcement cage having been lifted into place that same evening.

The reinforcement work for the head foundation with the integrated anchor rods as a connection for the signal bracket to be fitted later was commenced the next morning.

The prefabricated concrete element was placed over the lost formwork, the anchor rods were aligned for the final time and the head foundation was concreted at around midday.

Construction panel

Client:

Depenbrock Bau GmbH & Co. KG, 32351 Stemwede

Construction time:

Around 40 hours, 18./19.11.2023

Scope of work:

Installation of the foundation for a signal bracket with head foundation

HERING reference projects Foundation Construction Train:

Heavy duty machinery and Foundation Construction Train: News

Only a few days until InnoTrans 2026: HERING looks forward to Berlin

Preparations are in full swing: From September 22 to 25, 2026, the international rail industry will gather in Berlin for InnoTrans. HERING will be there too – and invites you to personal discussions about solutions for today’s and tomorrow’s rail infrastructure.

 

Meet us at:

Messe Berlin, Hall 25, Stand 365

September 22–25, 2026

 

HERING at InnoTrans 2026

What Awaits You at HERING?

At our booth, we showcase the full range of our services – from modular system solutions to specialized technology and innovative innovations:

At InnoTrans, HERING once again demonstrates how diverse competencies within a corporate group work together: planning, development, manufacturing, construction, and service – all from a single source.
 

HERING Stand Party

We would like to end the trade fair day on Wednesday, September 23, 2026, starting at 6:00 PM, together with you. Therefore, we cordially invite you to our HERING Stand Party!

Look forward to a relaxed evening in a pleasant atmosphere, good conversations, and the opportunity to reflect on the trade fair day with our team and guests.
 

Visit us in Hall 25, Stand 365. We look forward to seeing you!

Banner Innotrans 2026
EMAS-Logo

HERING sustainability

At HERING, we see ourselves as pioneers in the field of sustainability. As early as 1996, we were the first construction company in Germany to obtain EMAS certification. Every three years, we publish an environmental statement documenting our goals and how we have achieved them. Actually, for the first time, we published a sustainability report with an integrated environmental statement in accordance with EMAS - a logical next step in view of our ecological and social responsibility. It documents how we deal internally and externally with the issues that are essential to our future viability.

Exhibitions / Events

Only a few days until InnoTrans 2026: HERING looks forward to Berlin

Preparations are in full swing: From September 22 to 25, 2026, the international rail industry will gather in Berlin for InnoTrans. HERING will be there too – and invites you to personal discussions about solutions for today’s and tomorrow’s rail infrastructure.

 

Meet us at:

Messe Berlin, Hall 25, Stand 365

September 22–25, 2026

 

HERING at InnoTrans 2026

What Awaits You at HERING?

At our booth, we showcase the full range of our services – from modular system solutions to specialized technology and innovative innovations:

At InnoTrans, HERING once again demonstrates how diverse competencies within a corporate group work together: planning, development, manufacturing, construction, and service – all from a single source.
 

HERING Stand Party

We would like to end the trade fair day on Wednesday, September 23, 2026, starting at 6:00 PM, together with you. Therefore, we cordially invite you to our HERING Stand Party!

Look forward to a relaxed evening in a pleasant atmosphere, good conversations, and the opportunity to reflect on the trade fair day with our team and guests.
 

Visit us in Hall 25, Stand 365. We look forward to seeing you!

Banner Innotrans 2026