Modernisation at Stuttgart Feuerbach Station

Successful Project in Summer 2025

In summer 2025, our HERING Infrastructure Systems team successfully completed a major modernisation project at Stuttgart Feuerbach station on behalf of ARGE Eiffage Außenbahnsteig. The project focused on constructing a new platform and installing two modern system platform roofs.

Modernisation at Stuttgart Feuerbach Station

Modernisation at Stuttgart Feuerbach Station

New platform in May

The first stage in May involved building a 47-metre-long platform in modula® light design, directly connected to the existing conventional platforms. The modular construction allowed flexible adaptation to site conditions. Thanks to smooth coordination with other trades and precise scheduling with railway operations, the team was able to work efficiently and on time.
 

New platform roofs in June

June saw the installation of two roofs from the “Evolution” product line:

• Evolution 2020 Type 3: approx. 30 m long, installed in early June
• Evolution Typ 4 (single-column design): approx. 24 m long, installation starting 4 June

Both roofs are made of high-quality steel structures and were precisely integrated into the existing station environment. Despite their different designs, they create a cohesive and modern overall appearance.
 

Enhanced comfort for passengers

The new platform and two roofs have significantly upgraded the station:

• Improved accessibility
• Increased waiting comfort
• Attractive design for a welcoming station environment

 