Extensive Drilling Work in Two-Shift Operation
To complete the extensive workload within the scheduled timeframe, the team worked in a two-shift operation. The scope of work included:
- 16 reinforced bored piles
- 16 unreinforced bored piles
- 7 gravel piles
Premiere: Bored Pile Walls with the Foundation Construction Train
A special feature of this operation: For the first time, bored pile walls were constructed using the Foundation Construction Train. This allowed the team to successfully implement another application of the Foundation Construction Train in practice.
With the completion of the 39 boreholes, another important section of the Rhine Right Corridor rehabilitation has been finished – a strong result for the HERING foundation engineering team and another milestone for the use of the Foundation Construction Train.
Right Rhine Corridor Modernisation: Experience the Construction Site in Action!
How is work progressing? Which machines are being used? And what challenges are our teams tackling on site?
Our YouTube playlist dedicated to the Right Rhine Corridor Modernisation Project takes you behind the scenes, with regular video updates and fascinating insights into the construction work.
Watch now and subscribe to our YouTube channel so you don't miss any upcoming videos!