Menü
Foundation Construction Train
Track Foundations with HERING

Reference project track-foundation-laying train: Foundation for a signal bracket in Hamburg

A pile was driven in as the foundation for a signal bracket during the construction of the new S4 S-Bahn (suburban) railway link (Hamburg – Bad Oldesloe). The foundation was located on an embankment between the tracks of the S1 S-Bahn rail link and the mainline railway – it was therefore not possible to access it from the outside – but that was a situation for which the track-foundation-laying train was literally designed for.

The track-foundation-laying train allowed the workers to complete the foundation for a signal bracket in an inaccessible location within less than 40 hours – and without the need to dismantle any railway infrastructure. A total success!

Vorschaubild YouTube Video

Foundation in just 40 hours - the work flow:

2.00 a.m.: The shoring work began at the foundation point once the construction track had been installed. The track-foundation-laying train was prepared at a nearby suburban railway siding at the same time. The foundation pipe (DN 813) was attached to the hydraulic vibrator and vibrated 6.5 metres into the ground along with the welded-on side plates once the track-foundation-laying train had been positioned at the foundation point. The track-foundation-laying train was then converted on site to the Kelly drilling method for the purposes of boring out the foundation pipe down to the base.

The foundation pile was concreted with the reinforcement cage having been lifted into place that same evening.

The reinforcement work for the head foundation with the integrated anchor rods as a connection for the signal bracket to be fitted later was commenced the next morning.

The prefabricated concrete element was placed over the lost formwork, the anchor rods were aligned for the final time and the head foundation was concreted at around midday.

Construction panel

Client:

Depenbrock Bau GmbH & Co. KG, 32351 Stemwede

Construction time:

Around 40 hours, 18./19.11.2023

Scope of work:

Installation of the foundation for a signal bracket with head foundation

HERING reference projects Foundation Construction Train:

Heavy duty machinery and Foundation Construction Train: News

KRC910 during the lifting of the derailed locomotive
Special Operation in Sweden: KRC 910 Returns Derailed Locomotive to the Tracks
Specialist deep foundation drilling in Haan-Gruiten
Four Bored Piles for a Pedestrian overpass in Haan-Gruiten
Foundation Construction Train, Walluf
Rhine Right Corridor Rehabilitation: 39 Boreholes in Walluf
KRC1200-2 during bridge installation
Heavy-Duty Operation for IDEFIX in Karlsruhe-Durlach

Exhibitions / Events

No dates at the moment
Icon Social Media Auswahl